Investment, Trade and Industry Minister Datuk Seri Johari Abdul Ghani has set out tougher measures to stop data centres reserving grid capacity they do not use, often called “phantom demand”. He spoke at a Bursa Malaysia event on 10 November.
What has changed
- A much higher connected load charge. The charge for capacity reserved on the grid has risen from RM8.50 to RM89.64 per kW.
- Separate planning. Data centre electricity demand is now planned and managed separately from household and traditional industrial demand.
- A new ultra high voltage tariff under which operators pay the full cost of the transmission upgrades they need.
- Tighter efficiency targets for power, water and carbon usage effectiveness.
- Support for off-grid supply. The Energy Commission is fast-tracking a self-generation framework, and developers are encouraged to use gas, solar, hydropower and battery storage.
The numbers behind the decision
- Data centres accounted for 43.9% of approved investment in the first half of 2026, up from 0.4% in 2021.
- Malaysia has approved 117 data centres with a combined maximum demand of about 23,500 MW. Of these, 55 are operating and 19 are under construction.
- Another 24 applications are on hold while power and water availability is checked.
- Data centres use about 7% of the country’s electricity, a share that Bursa Malaysia’s chairman said could reach 31% by 2035.
These measures follow the government’s decision in February 2026 to stop approving new data centres that are not for AI, because of concerns over power and water supplies.
What it means for businesses
- Colocation and cloud prices may rise as operators pass on higher grid and efficiency costs.
- Capacity may be tighter in popular areas, so book space and power early if you are planning a move or expansion.
- Efficiency matters more. Consolidating and virtualising servers, and retiring old hardware, can cut both your power bill and your rack space.
Sources: The Star: Curbs on data centre grid hoarding; Malay Mail: Malaysia freezes new non-AI data centres (February 2026).